Silkem – Slovenia

Project statistics

Monitoring of consumption

Communication with existing central control system

Data storage 

Situation before the contract and client requirements

Client used old meters from 1950 with no communication system in place. 

In order to check energy consumption, manual control of 114 electricity meters had to be performed. 

The client wanted 114 new electricity meters. 

The client requested automatic acquisition of data on the consumption of electricity, power, current and voltage.

Resalta solution

Installation of 114 new meters with Modbus communication systems in 4 electricity substations.

The new meters communicate data to the server via fiber optics.

Want to see more?

Download our brochure.

Terms and conditions.

By subscribing to our newsletter you agree to receive e-mail communications from Resalta d.o.o. The aim of our newsletter is to keep visitors to the website, partners, clients and the general public informed of the work Resalta does, its new projects, developments, upcoming events as well as news concerning energy efficiency and renewables. The frequency of the newsletter issues will be at most monthly, with possible exceptions for unscheduled yet important news. We reserve the sole right to either modify or discontinue the newsletter, at any time and without notice to you. We take your privacy seriously and will never communicate or sell your information to third parties. You can unsubscribe from the newsletter at any time.